Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Just Posted

COTR honours Orange Shirt Day

A virtual event to raise awareness about Orange Shirt Day is being hosted early on Sept. 22

Invermere gets new CAO

Invermere found his new CAO after a long period of research.

Radium council discusses short term rentals

RHS council are elaborating the second draft plan for STR

Farmers’ Institute report highlights emerging local food scene

Beef cattle ranching remains mainstay of valley agriculture

B.C. records 98 more COVID-19 cases, most in Lower Mainland

One new senior home outbreak, Surrey Memorial outbreak over

PHOTOS: 2nd calf in a month confirmed among Southern Resident killer whale pod

Center for Whale Research said they will eagerly await to observe the calf to evaluate its health

97 distressed horses, cats and dogs seized from farm in Princeton

RCMP assisted as BC SPCA executed search warrant

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

$250K reward offered as investigation continues into Sea to Sky Gondola vandalism

Police also asking for specific footage of Sea to Sky highway around time of incident

Trudeau ‘disappointed’ by RCMP treatment of Sikh officers over mask issue

World Sikh Organization of Canada said taking Sikh officers off the front lines constitutes discrimination

Liberals reach deal with NDP on COVID-19 aid bill, likely averting election

NDP and the Liberals have reached an agreement on COVID-19 sick-leave

Most Read