Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Canal Flats pavilion gets a financial boost

Trust provides over $1.9 million for 12 community projects

Victory for the Rockies in first season game

Catch the next game Friday, Sept. 20th against the Thundercats

Local climate action strike

Friday, September 20th strike in downtown Invermere

RCMP Report

Some of the more interesting callouts for Columbia Valley RCMP

Third instance of Trudeau in skin-darkening makeup emerges

Another instance of Trudeau using makeup to darken his face has emerged, within 24 hours of the first

Nelson man accused of swimming naked at Toronto aquarium expected to plead guilty

David Weaver, of Nelson, was arrested and charged in October of last year

VIDEO: Party leaders react to Trudeau’s brownface photo bombshell

Fallout from Justin Trudeau’s brownface photo, and two other instances, sure to dominate campaign

35 of 87 dogs in 2018 Williams Lake seizure were euthanized, BC SPCA confirm

The dogs did not respond to the behaviour modification and remained terrified of humans

B.C. ‘tent city’ disputes spark call for local government autonomy

UBCM backs Maple Ridge after province overrules city

B.C. drug dealers arrested after traffic stop near Banff turns into helicopter pursuit

Antonio Nolasco-Padia, 23, and Dina Anthony, 55, both well-known to Chilliwack law enforcement

Nelson man pleads guilty in assault that killed man sitting on sidewalk

Miles Halverson is guilty of manslaughter in the June 2018 death of Matt Reeder

Most Read