Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

101-year-old man targets 101 block fundraising walk for food bank

A centenarian in Invermere has embarked on a new adventure to raise money for the food bank.

Entrepreneur implements safety measures to cope with long weekend

Ryan Haynes prepares for both the pandemic and for the Victoria Day long weekend in May.

Wings Over the Rockies encourages nature viewing during pandemic

Three local photographers and Wings supporters offer nature viewing tips.

Hospital chief of staff provides guidance on COVID-19 and the Columbia Valley as we open up

Chief of staff says: “COVID-19 … is still here and is not going away any time soon.”

Our community news matters

Guest editorial by Arnold Malone

B.C. legislature coming back June 22 as COVID-19 emergency hits record

Pandemic restrictions now longer than 2017 wildfire emergency

B.C.’s essential grocery, hardware store employees should get pandemic pay: retail group

Only B.C.’s social, health and corrections workers are eligible for top-ups

COLUMN: Canada needs to remember rural communities as thoughts turn to pandemic recovery

Small towns often rely on tourism, which has been decimated by COVID-19

Edmonton, Vancouver and Toronto vying to be NHL hubs, but there’s a catch

The NHL unveiled a return-to-play plan that would feature 24 teams

B.C. sees 9 new COVID-19 cases, one death as officials watch for new cases amid Phase Two

Number of confirmed active cases is at 244, with 37 people in hospital

Introducing the West Coast Traveller: A voyage of the mind

Top armchair travel content for Alaska, Yukon, BC, Alberta, Washington, Oregon and California!

Nanaimo senior clocked going 50 km/hr over limit says her SUV shouldn’t be impounded

RCMP say they can’t exercise discretion when it comes to excessive speeding tickets

Illicit-drug deaths up in B.C. and remain highest in Canada: chief coroner

More than 4,700 people have died of overdoses since B.C. declared a public health emergency in early 2016

CMHC sees declines in home prices, sales, starts that will linger to end of 2022

CMHC said average housing prices could fall anywhere from nine to 18 per cent in its forecast

Most Read