This week’s announcement means continued work on the Trans Mountain pipeline could be delayed for years. (File photo contributed by KINDER MORGAN)

Trans Mountain expansion could be delayed for years: experts

The federal government will have to redo its consultation with all affected First Nations along the pipeline

The Federal Court of Appeal’s decision to quash Ottawa’s approval of the Trans Mountain pipeline expansion is likely to delay the project for years, legal and political observers say.

The ruling means the National Energy Board must consider the impacts of increased tanker traffic on the marine environment and the federal government must consult more meaningfully with First Nations.

The energy board should first conduct its new review, which will involve receiving written submissions, consulting with Indigenous groups and holding hearings, said Chris Tollefson, a law professor at the University of Victoria.

The board’s first review took two years, and while the new assessment will be focused specifically on tanker traffic, Tollefson said the board must seriously consider the effects on endangered southern resident killer whales.

“The reality is that this proposal as currently planned would impact orcas unless it is changed,” said Tollefson, who represented BC Nature and Nature Canada during the first energy board review.

READ MORE: Federal court quashes approval of Trans Mountain pipeline expansion

There are only 75 southern resident orcas left and few have reproductive potential. The project would have a serious impact unless design changes were made, such as altering shipping routes, reducing tanker speeds or the number of vessels, Tollefson said.

“In light of what the court had to say, I don’t think that should be hurried. I think it needs to be done right. It’s a central feature of this project.”

Once the board issues a new recommendation to cabinet, the federal government will have to redo its final phase of consultation with all the affected First Nations along the pipeline route.

Eugene Kung, a lawyer who has worked for project opponent the Tsleil-Waututh Nation, warned that if Ottawa tries to rush consultation, the project could just wind up back before the court.

“The federal government continues to take direction from the courts and interpret it through a lens of, ‘What is the least we can do?’ … In the age of reconciliation, but also if the federal government is looking to avoid future appeals, they need to start aiming for something higher than the floor,” said Kung.

The court ruled that Canada must not only listen to First Nations during consultation, but also seriously consider their specific and real concerns and provide a response, including accommodations where necessary.

READ MORE: Trudeau determined to build pipeline despite court ruling

For example, the Coldwater Indian Band in British Columbia’s southern Interior raised concerns about the pipeline route passing through an aquifer that is the sole supply of drinking water for the First Nation’s main reserve, but the government did not reroute the pipeline or provide a new water source.

“They were undertaking the (final) consultations with First Nations in a rushed manner and not taking the time to listen, to try to accommodate and to have a genuinely two-way conversation, which takes longer than listening, taking notes and relaying them to decision-makers,” said Kathryn Harrison, a political scientist at the University of British Columbia.

It’s highly improbable Trudeau’s government will be able to get the board review and Indigenous consultations done before the next election in the fall of 2019, said Harrison, who added that it’s difficult to say how the ruling will affect the Liberal government’s chances.

“How does Justin Trudeau respond to (Alberta Premier) Rachel Notley’s directives to him and withdrawal from the climate plan?” she asked. “What steps can he take to reassure the oil industry that Canada knows what it’s doing in reviewing major projects?

“To what degree does the government convince Canadians that buying this pipeline and committing to build a new one was a good investment of taxpayers’ dollars?

“It really depends on what the Trudeau government does.”

Notley announced Thursday she was pulling Alberta out of the federal climate plan until Ottawa gets the pipeline expansion back on track. She demanded that Trudeau appeal the ruling to the Supreme Court and hold an emergency session of Parliament.

READ MORE: Notley pulling Alberta out of federal climate plan

Trudeau said Friday he is committed to getting the project done “the right way.” He suggested he will follow the Appeal Court’s guidance on how to proceed.

“We are taking the time now to understand the court ruling, which addresses two things that are very important to this government — getting the science and the environmental protections right, and making sure we are walking forward in a true path of reconciliation and partnership with Indigenous Peoples,” Trudeau said after an event in Oshawa, Ont.

“We’re going to continue to move forward to get this pipeline built in the right way by acknowledging what the court has said.”

Even if the federal government did seek leave to appeal and the Supreme Court agreed to hear the case, that would take 18 months to two years, experts said.

The expansion project would triple the bitumen-carrying capacity of the Trans Mountain pipeline between near Edmonton and Metro Vancouver and increase tanker traffic in the Burrard Inlet sevenfold.

Kinder Morgan Canada Ltd. first announced the proposal in 2012 and shareholders voted Thursday to sell the pipeline to Canada for $4.5 billion.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Young Hearts Triathlon

Annual event saw racers of all ages swim, bike, and run their way to a cheering finish line on Saturday, July 13th

Museum presents old time film festival

Series of six films Saturday, July 20th through Sunday, July 21st at museum

Peddling the practice of bikepacking

Growing sport of backcountry biking in the Valley

Balancing aesthetics and affordability in Canal Flats

Canal Flats Council briefs of July 8th

Rich the Vegan scoots across Canada for the animals

Rich Adams is riding his push scooter across Canada to bring awareness to the dog meat trade in Asia

Vancouver Island teens missing after vehicle found ablaze near Dease Lake, BC

RCMP say a body discovered nearby not one of the missing teens

A year later, ceremony commemorates victims of the Danforth shooting

It’s the one-year anniversary of when a man opened fire along the bustling street before shooting and killing himself

Japanese Canadians call on B.C. to go beyond mere apology for historic racism

The federal government apologized in 1988 for its racism against ‘enemy aliens’

B.C. VIEWS: NDP pushes ahead with Crown forest redistribution

This isn’t the time for a radical Indigenous rights agenda

Two dead in two-vehicle crash between Revelstoke and Golden

RCMP are investigating the cause of the crash

Ottawa fights planned class action against RCMP for bullying, intimidation

The current case is more general, applying to employees, including men, who worked for the RCMP

Alberta judge denies B.C.’s bid to block ‘Turn Off the Taps’ bill

He said the proper venue for the disagreement is Federal Court

Most Read